The path for Duxbury to erect a Community Scale Wind Turbine began in 2008 during meetings of the Alternative Energy Committee. Here is the timeline we envision to complete our goal:


     October 2009--Wind Facilities Site Assessment Report by DNV Global.


     December 2009--Bylaw Presented to Board of Selectmen, Recommended for Approval.


     January 2010--Bylaw Presented to Planning Board, Board voted to Recommend for Approval.


     January 2010--Bylaw Presented to Finance Committee, Committee voted to Recommend for Approval.


     March 15 2010--Town Meeting approves By Law amendment to establish permit process for a Municipal Turbine.


     June 2010--Grant Approved for Feasibility Study on Town Owned Land identified by Site Assessment Report as a viable target.


     Summer 2010 to Summer 2011--Feasibility Study